Saudi Arabia is ending the contract in NEOM to build three dams for TROJENA

A March 25, 2026, update from the contractor on the TROJENA site says the project owner, NEOM, has ended the deal to build three dams and a linked structure called “The Bow.” The notice took effect March 29, with the work described as about 30 percent complete. The contractor said the remaining backlog was about €2.8 billion, or roughly $3.2 billion, and that termination and shutdown costs will be reimbursed under the contract. The contract was announced in January 2024 as a roughly $4.7 billion effort to create a freshwater lake about 1.7 miles long in the mountains of TROJENA.

A “termination for convenience” is a contract clause that lets a client stop work without claiming the builder did anything wrong. In everyday terms, it is closer to hitting pause on a purchase order than losing a lawsuit.

That legal language matters because it shapes what happens next. The public update did not include a revised timeline, a replacement contractor, or a new design for the lake system.

For now, the biggest takeaway is uncertainty. When a project’s centerpiece is a lake, even a short pause can ripple into hotels, roads, and the jobs that depend on a fixed schedule.

Italian officials have described TROJENA as a high-elevation development in northwestern Saudi Arabia, around 31 miles from the Gulf of Aqaba coastline. The same materials point to peaks reaching about 8,530 feet, which is high enough to be noticeably cooler than the lowlands.